Navigating the PreCon PSR: PreCon PSR Dashboard
Modified on: Tue, Aug 24 2021 6:12 PMThe Precon PSR Dashboard page is available in two modes
- Dashboard mode (default): a graphical view of the PreCon PSR metrics
- Tabular: data presented in a simple table view without any graphics
Dashboard View
This page shows detailed metrics for a given selected: Job and Period (Year Month). You filter the page by using the “Job Code – Name” drop down menu. Please be advised that a distinct Job, Year, and Month need to be selected for this dashboard to function.
Below this image is a reference table for each visual on the page, lettered A - DD.
Visual ID (A-DD) |
Description |
Source/Notes |
|
A |
Original Contract: The Original Precon Contract Value |
This will tie to the PSR Box 2: Original Contract |
|
B |
Current Contract: The Original Contract Value + All Posted OCO’s before the year and month selected |
This will tie to the PSR Box 2: Current Contract |
|
C |
Revenue Forecast: The forecasted revenue for this Precon job |
This will tie to the PSR Box 1: Revenue Forecast |
|
D |
Cost Forecast: The projected final cost |
This will tie to the PSR Box 1: Cost Forecast |
|
E |
Spent to Date: How much has been spent to date on the Precon job |
This will tie to the PSR Box 1: Spent To Date |
|
F |
PM Forecasted Fee: How much does the PM forecast us to earn/lose on this Precon job |
This will tie to the PSR Box 1: Projected Gain Loss |
|
G |
Billed to Date: The total amount we have billed this client for this job irrespective of period selected |
This will tie to PSR Box 5: Gross Billings |
|
H |
Received To Date: How much has this job’s owner paid us |
Sum of all payments up to and including the selected Year and Month |
|
I |
Over 30: Receivables more than 30 days old and less than 60 days old |
Invoice – Adjustments – Payments where the invoice age is between 31 – 60 days old |
|
J |
Over 60: Receivables more than 60 days old and less than 90 days old |
Invoice – Adjustments – Payments where the invoice age is between 61 – 90 days old |
|
K |
Over 90: Receivables more than 90 days old |
Invoice – Adjustments – Payments where the invoice age is more than 90 days old |
|
L |
Construction Budget Variance %: Client’s current budget vs Swinerton’s projected budget |
|
|
M |
PreCon Duration: The total difference from the Precon start to the projected Precon completion. The target is = 6 * number of jobs we are examining for a specified period.
|
Red: if the PreCon Duration is more than 6 months Green: if the PreCon Duration is less than 6 months |
|
N |
Construction Value Engineering %: What percent of the overall Swinerton Budget is Value Engineering? |
< 3% = Target < 5% = Good >= 5% = Bad |
|
O |
Critical Subs Committed by 100% DD: How many critical subcontractor trades have been committed at 100% Design Document? |
5 = Good/Green
|
|
P |
Construction Allowance %: What percent of the overall Swinerton Budget is an Allowance? |
< 1% of budget = Target |
|
Q |
Project Team: The count of filled roles and each staff person at Swinerton in these roles: Project Champion, Estimator, and Project Champion |
<2 = Bad 3 = Good |
|
R |
Similar Projects by Division: How many similar self-preform project has a division preformed? |
3 or More Green Less than 3, Orange Otherwise, Red |
|
S |
Similar Self Preform Projects: Number of self-perform projects of similar dollar value, product type, and complexity |
3 or More: Good/Green Less than 3: Orange Otherwise: Bad/Red |
|
T |
Projected Document Stage at GMP: At what design stage is a final GMP/Lump Sum contract value expected?
|
Greater than 75% CDs Green 100% DDs to 75% CDs Orange Less than 100% DDs Red
|
|
U | Current Estimate Document Stage: What design package are we using in this estimate? | Intended uncolored | |
V |
Phasing & Logistics Plan: Did Operations Create a Logistics Plan? |
Yes Green No Red |
|
W |
Self Perform Scrub the Documents: Did Self-Perform Scrub the documents? |
Yes: Green No: Red |
|
X |
Client Alignment: What was the difficulty of negotiating the contract terms? |
Mutually Agreeable Green Moderate Yellow Terms were highly modified Red Can't modify the terms Red
|
|
Y |
Architect Alignment: How aligned are we with the Architect. |
Strong Alignment Green Moderate Alignment Orange Not Aligned at all Red
|
|
Z | Contract Negotiations: How aligned are we with this Client/CM? |
Strong Alignment Green Moderate Alignment Orange Not Aligned at all Red
|
|
AA |
# of SP Trades: The number of self-perform trades (if any) |
Intended uncolored | |
BB |
Critical Item 1: An item of high priority to consider on this project. |
Intended uncolored |
|
CC |
Critical Item 2: An item of high priority to consider on this project. |
Intended uncolored |
|
DD |
Critical Item 3: An item of high priority to consider on this project. |
Intended uncolored |
Tabular View
This is a tabular on the PreCon PSR Dashboard. It is intended to contain all the PSR metrics in a summarized format for those with visualizing data as a table rather than the dashboard.