CMiC - Logs/Reports
How To's on how specific reports pull their information/calculations
-
Gallagher Report
Gallagher Report No need to keep a separate excel spreadsheet, you can run this report and send it to Gallagher. How the Report pulls the information: The report pulls all subcontracts (Pending or In Process) The report pulls the Contact Name that is marked as the Primary Contact in Project Partner/Contact Directory (They also have to have a PM Role and since they are all subcontractors, they should all have the Role SUBRFI) If you are finding that addresses are not showing, please check the contact and make sure they are the primary contact and that they have a PM Role on the project.
-
Navigating the PSR
Navigating the Project Status Report (PSR) Note: This report includes a series of smaller reports with project data from various areas of CMiC to create a comprehensive overview of the project. This report is used on a monthly basis to communicate to Division Management, Corporate Management and Swinerton business partners the status of each project. STEP 1: Always make sure you have gone into Contract Forecasting and clicked Go > Refresh All before you try to print your PSR STEP 2: Expand Reports STEP 3: Expand Budget & Cost Reports STEP 4: Expand Job Costing STEP 5: Click Project Status Report - PM STEP 6: Enter the information for the project you want to run the PSR for Note: If you are a Main Job and have Self Perform projects that are going to be pulling through to your PSR, make sure to change the Job Status to All so that all Self Perform project amounts (including those that might be closed) pull through. (This especially affects Box 12 Cash Flow) Note: No need to change the Current Period/Prior Period unless you are specifically running a report for a prior period STEP 7: Click Run Report BOX 1 - JOB FORECAST STATEMENT SUMMARY Column Details (from left to right): A Name: Phases/Categories are summarized into Types: Labor, Rentals, Materials, Subcontracts, Admin and Other, Insurance Taxes and Bonds, Allowance, Contingency, Buyout, Non‐Reimbursables, Joint Venture, Claim Costs, Claim Recovery, Contract Fee, Adjustments. B Spent This period: Costs posted to the job during the month the report is for C Spent To Date: Costs posted to the job since inception D Spent/Committed Total: The higher of Spent or Committed plus Spent outside of Commitment E Cost to Cmplt Inc. PCIs Cost to Complete as calculated or overridden manually in field or adjusted via the Pop up + Unposted PCIs F Cost Forecast: Cost Forecast as calculated or overridden in Contract Forecasting. This should be the projected final cost to complete the project including all anticipated change order work. G Current Revenue Budget: Current Contract value with the Owner. H Anticipated COs: Revenue Forecast – Current Revenue Budget = Anticipated COs. This is a calculation that reflects any revenue forecast reductions that were made in PCI Projections, or any revenue forecast overrides that were made in Contract Forecasting. If such adjustments have been made, this number will be different than the Total External PCIs recorded in Box 2, which is the amount the Owner sees on the PCI log. I Revenue Forecast: Revenue Forecast as calculated or overridden in Contract Forecasting. This should be the projected final contract value with the Owner at the end of the project including all anticipated change orders. J Projected Gain/Loss: Revenue Forecast – Cost Forecast = Projected Gain/Loss. The difference between what it is going to Cost to do the work and what the Owner is going to pay us. The FINAL Fee when the job is closed. K One Month Variance: Prior Month Projected Gain/Loss – This Month Projected Gain/Loss = One Month Variance L % Cost Complete: Spent To Date/Cost Forecast Row Details (from Top to Bottom): M Contract Fee: Should exist on all jobs (Revenue Budget only) and is Phase/Category 999999‐79999. N Adjustments: Combines PM Cost and Revenue Adjustments and Financial Manager accruals. Refer to “Forecasting Philosophy” handout for details on when and how to use Adjustments. O Total: Job Totals for each Column. Total under Projected Gain/Loss is your PM Projected Fee. P General Conditions: Total of Phases and Categories on the job assigned to Phase Type “GC”, (value is already included in above.) Q Self-Performed Work Total of Phases and Categories on the job assigned to the following Phase Types (CARP, CONC,DRYW,SOLA,SPGC or SPW(value is already included in above.) BOX 2 - CHANGE ORDER STATUS - EXTERNAL PCIs Note: Data for this report is from the External (CTO, ALLOWANCE & CONTINGENCY types) & TRANSFER Potential Change Items and Owner Change Orders. Statement Summary, if any PCI forecasts have been adjusted in PCI Projections, or any Revenue Forecast amounts have been overridden in Contract Forecasting. Use comment 2 if amounts are not close. Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report C No.: Number of PCIs in each Status D Current Amount: Dollar value from the “Revenue Amount” column of the PCIs in each Status E Days: Number of days from the “Estimated Days Impact” field in the PCI header for all the PCIs in each Status Row Details: F Original Contract: Original Contract value with the Owner as shown in the Owner Change Order module. G Posted OCOs: All OCOs that have been posted. H Current Contract: Original Contract + Posted OCOs I Approved (Unposted) All PCIs with a Status of "Approved" but have not been Posted J Submitted All External PCIs with a Status of “Submitted” – Proceeding or Not Proceeding. K Pending / Resubmit: All External PCIs with a Status of "Pending" - Proceeding or Not Proceeding All External PCIs with a Status of “Revise and Resubmit” – Proceeding or Not Proceeding. L Denied: All External PCIs with a Status of “Denied” ‐ Proceeding or Not Proceeding. Denied status should never be used for Cancelled PCIs. Use Comment 2 if Denied PCIs exist. M Total External PCI’s: Total of Submitted, Revise & Resubmit, Pending and Denied External PCIs. Use Comment 2 if this amount is less than the Total Anticipated CO’s in report 1 Job Forecast Statement Summary. N Projected Final: Current Contract + Total External PCIs. This amount should equal the total the Owner sees on the PCI Log. It may not match the total of the Revenue Forecast Column of Report 1 Job Forecast O Self Perform Unposted: Total of all Self Perform projects Unposted External PCI's BOX 3 - EXTERNAL PCIs PROCEEDING WITHOUT OCO Note: Data for this report is from the External (CHANGE TO OWNER, ALLOWANCE & CONTINGENCY types) & TRANSFER Potential Change Items and Subcontract Change Orders. Column Details (from left to right): A Proceeding: External PCIs with the status “Proceeding” not included in a posted OCO. B No.: Number of External PCIs with the status “Proceeding” not included in a posted OCO. C Current Amount: Dollar value of External PCIs with the status “Proceeding” not included in a posted OCO. Amount Proceeding should not exceed amount Owner Directed to Proceed. Use Comment 3 if condition exists. D Owner Direction: Includes data from the “Owner Direction” field in the header of External PCIs. E Proceed: Dollar value of External PCIs not included in a posted OCO with the Owner Direction of Proceed. F Under Protest: Dollar value of External PCIs not included in a posted OCO with the Owner Direction of Proceed Under Protest. Use Comment 3 if amounts exist in Under Protest. G Advanced SCO Issued: Subcontract Change Orders issued against External PCIs not in a posted OCO. H No.: Number of Subcontract Change Orders issued against External PCIs not in a posted OCO. I Amount : Dollar Value of Subcontract Change Orders issued against External PCIs not in a posted OCO. Use Comment 3 if Advanced SCOs exist. Row Details: J Submitted: External PCIs with the status “Submitted” for each column. K Revise & Resubmit: External PCIs with the status “Revise & Resubmit” for each column. L Pending: External PCIs with the status “Pending” for each column. M Denied: External PCIs with the status “Denied” for each column. N Total External PCI’s: Total External PCIs for each column. BOX 4 - UNPOSTED INTERNAL PCIs Note: Data for this report is from the Internal (NO CHANGE TO OWNER, BACKCHARGE types) Potential Change Items. Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report C No.: Number of Internal PCIs not Posted. D Current Amount: Dollar value of Internal PCIs not Posted. Row Details: E NCTO’s: Unposted Internal PCIs with Type No Change To Owner. F BC’s: Unposted Internal PCIs with Type Backcharge. Use Comment 4 if large number of BCs exist. G Total Internal PCI’s: NCTO’s + BC’s. Total Unposted Internal PCIs. BOX 5 - BILLINGS Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report Row Details: C Gross Billing: Total amount billed to the Owner on the job. D Gross Cost: Total Cost on the job. Should match the Total of the Spent to Date Column in Report 1 Job Forecast Statement Summary. E Earned Fee: (Gross Cost/Total Cost Forecast in Report 1) * Total Gain/Loss in Report 1. If projecting a loss, this will equal the Total Gain/Loss in Report 1. Since the Cost Forecast includes unposted PCIs, the Total Gain/Loss should include the potential Fee on those unposted PCIs, or our Earned Fee will be understated. (This is a big difference from our previous fee projection philosophy.) F Over (Under) Billing: Gross Billing – (Gross Cost + Earned Fee). Use Comment 5 if under billed or significantly over billed. G % Est Fnl Cont Billed: Gross Billing/Total Revenue Forecast in Report 1 Job Forecast Statement Summary. % Billed of the estimated final contract value with the Owner. H Retention Held: Total retention held by the Owner. BOX 6 - RECEIVABLES Note: Data for this report is from the A/R Aged Report (See below for screenshot of where this report can be found on your treeview) Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report Row Details: C Total Receivables: Total Billed to the Owner not paid. D Current: Total Billed to the Owner and outstanding for 30 days or less. E Over 30: Total Billed to the Owner and outstanding for over 30 days, and up to 60 days. Use Comment 6. F Over 60: Total Billed to the Owner and outstanding for over 60 days, and up to 90 days. Use Comment 6. G Over 90: Total Billed to the Owner and outstanding for over 90 days. Use Comment 6. BOX 7 - FEE SUMMARY Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report NOTE: The "History" for the Last Period is taken after the Company WIP has been completed by all Financial Mangers. C % C: Percent Cost Complete - Calculation = Spent to Date / Cost Forecast D %RF Percent Return of Fee - Calculation = PM Forecasted Fee / Current Contract Value Row Details: E Main Project Forecasted Fee: Total from the Projected Gain/Loss Column of Box 1 Fee as reported by the Project Manager in Contract Forecasting. F All Self Perform Project Forecasted Fee: As each Self Perform project has its Contract Forecast updated, it will start to pull into the Main Job PSR with the same column calculations as the Main Job. NOTE: If the Current amount next to a Self Perform project is blank, please reach out to that PM to complete the forecast. NOTE: If the Self Perform project is closed, it will pull the final calculation of Revenue - Cost NOTE: For Self Perform projects with other companies (SAK, MD Builders, Timberlab) see below for what will/will not show on your PSR due to Union rules G Total Swinerton Forecasted Fee: Total of Main Project + all Self Perform project Forecasted Fee H Total Current Contract Fee Total of Main Project + all Self Perform Contract Fee I Total Variance: Total of Main Project + all Self Perform - Calculation = Forecasted Fee - Contract Fee. Use Comment 7 if any variance J Total Original Contract Fee: Total of Main Project + all Self Perform - Original Fee based on Original Contract K Shared Savings From Job Setup / Project Maint. OM User-Defined Fields L Savings Split (%) From Job Setup / Project Maint. OM User-Defined Fields BOX 8 - PROJECT MANAGEMENT Note: Data for this report is from the Project Management modules: Submittals, RFIs and Daily Journals (There should only ever be 7 DJs open/pending at a time). Note: Use Comment 8 in Forecast Comments if an explanation is warranted regarding risks related to any values reported. Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report Row Details: C Not Yet Submitted (Submittals): Number of Submittals with the status of: Anticipated. D Open (Submittals): Number of Submittals with the status of: Open, Pending Design Change, Received, Revise and Resubmit, Submitted. E Rejected (Submittals): Number of Submittals with the status of: Rejected, Submit Specified Item. F Closed (Submittals): Number of Submittals with the status of: Approved, Approved as Noted, Closed, Make Corrections Noted, For Information Purposes, No Exceptions Taken, Reviewed, Voided. G Total Open (RFIs) Number of RFIs not closed or voided. H Total Overdue (RFIs): Number of RFIs where the date due is less than the period end date. I Total (Daily Journals): Total number of Daily Journals on the project. J Open (Daily Journals): Number of Daily Journals not yet Submitted.There should only ever be 7 of these.If there are more, please ask that they get submitted BOX 9 - SCHEDULE Note: Data for this report is from the Forecast Comments button/pop‐up entered in Contract Forecasting to be completed monthly by the Project Manager. Column Details (from left to right): A Completion Date (Current): Date as entered in Forecast Comments for the current period. B Duration in Mos (Current): Number of months from Contract Start Date entered in Project Maintenance General Tab. C % Complete (Current): % Complete based on the period end date and the Current Contract Completion date. ( Calculation is something like this: Contract forecast Date - Project start Date (in months ) /(projected project end date -project start date) D Completion Date (Last Period): Date as entered in Forecast Comments for the prior period. Row Details: E Schedule ID: Schedule ID for the monthly schedule update as entered in Forecast Comments. F Data Date: The data date represents the line in the sand between what is actual and what remains G Original Contract: Original Contract Completion date entered in Project Maintenance General Tab. H Current Contract: Current Contract Completion date as reflected in the Owner Change Order module. I Substantial Completion: Substantial Completion date for the monthly schedule update as entered in Forecast Commen s. J Final Completion: Final Completion date for the monthly schedule update as entered in Forecast Comments. K Date Sent to Owner: Date the monthly schedule update was provided to the Owner. L GCs Projected Through: Date General Conditions are projected through as entered in Forecast Comments. Use Comment 9 if earlier than Final Completion date. M Schedule Delay, PCIs: If Monthly schedule update reflects a delay to the project schedule, PCI numbers where the delay is being tracked as entered in Forecast Comments. BOX 10 - SAFETY Note: Data for this report is from the Forecast Comments button/pop‐up entered in Contract Forecasting to be completed monthly by the Project Manager. Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report Row Details: C JHA’s Prepared: Total number of Job Hazard Analyses prepared (current month). D Safety Meetings Held: Total number of Safety Meetings held (current month). E Safety Orientations Held: Total number of Safety Orientations held (current month). F Pre‐Task Plans Prepared: Total number of Pre‐Task Plans prepared (current month). G Safety Audits Performed: Total number of Safety Audits performed (current month). H Safety Near Misses: Total number of Safety Near Misses (current month). I First Aid Cases: Total number of First Aid Cases (current month). J Recordable Incidents: Total number of Recordable Incidents (current month). K Lost Time Incidents: Total number of Lost Time Incidents (current month). BOX 11 - QUALITY Note: Data for this report is from the Forecast Comments button/pop‐up entered in Contract Forecasting to be completed monthly by the Project Manager. Column Details (from left to right): A Current: Data as of the period entered in “Current Year and Current Period” parameters when running report B Last period: Data as of the period entered in “Prior Year and Prior Period” parameters when running report Row Details: C Pre‐installation Meetings Held: Total Number of Pre‐Installation Meetings held for the entire project, not just the single month. D 1st Work inspections Held: Total Number of First Work Inspections held for the entire project, not just the single month. E Total Deficiencies: Total Number of Quality Deficiencies identified for the entire project, not just the single month. F Deficiencies Still Open: Number of unresolved Quality Deficiencies for the entire project, not just the single month. G Building Envelope Review By: Party who performed the Building Envelope review. BOX 12 - CASH FLOW Note: The data in this box is exactly the same as the separate report called "Job Cash Flow Report" which can be run by a Project Manager at any time of the month and found on the CMiC treeview under Reports/Job Costing/Job Cash Flow Report. Starting 1/16/2023, the calculations in this box will add the Main job and all the Self Perform jobs numbers together. The new Job Cash Flow Report will have all jobs on it so you are not needing to run multiple reports to validate. Column Details (from left to right): A Last Bill Date: Last date we billed the Owner B Last Receipt Date: Last date we received payment from the Owner C JTD Billing: Job to date amount billed to the Owner D JTD Cost: Job to date cost that has been charged to the job E Current Receivables: Billing amount outstanding with the Owner F Current Payables: Payables on the job (amount we currently owe to Subs, Vendors, etc) G Retention Receivables: Retention held by the Owner H Retention Payables: Retention held on our Subcontractors I Cash In: Amount we have been paid to date by the Owner (less current receivables and retention held) J Cash Out: Amount we have paid out to Subs, Vendors, etc (less current payables and retention held) K Net Cash In/Out: Cash In less Cash Out. Net cash flow on the job. COMMENTS BOX Note: Data for this report is from the Forecast Comments button/pop‐up entered in Contract Forecasting. Note: Comments are required to explain any abnormalities or address any potential risks reflected in the information reported in the respective sections. Comments can be up to 100 characters per field. 1. Job Forecast Statement Summary 2. Change Order Status – External PCIs 3. External PCIs Proceeding without OCO 4. Unposted Internal PCIs 5. Billings 6. Receivables 7. Fee Summary 8. Project Management 9. Schedule 10. Safety 11. Quality 12. Cash Flow
-
Job Cash Flow Report
As of 1/16/2023, the Main Job "Job Cash Flow Report" will show all the Self Perform job(s) numbers as well. This allows the project team of the Main Job to only run one report to validate the numbers on the PSR Box 12.
-
Unsigned Subcontract Change Orders
The Unsigned Subcontract Change Order (SCO) Log allows you to understand if your project has any unsigned/unexecuted SCO's. This log only shows SCO's that do not have an executed date. It also now (as of 6/17/2024) shows you if the SCO is currently being billed for (Billed Amount / Billed Flag 'Y') or had been billed and paid out (Paid Amount / Paid Flag 'Y') Best practice is to make sure that all commitments and SCO's are executed prior to being billed for. When an SCO comes back through Docusign executed, it should be attached to the SCO and the Executed Date in the bottom right corner be entered. If you start with this log when you are entering executed SCO's it will take you directly to the SCO and save you several clicks. We also have a formatted MIP that you can print out if needed. PM's, you should be checking this log before approving billing from a sub on an unsigned SCO.
-
Division Manager - SC/SCO Tracking Log
Located under Reports > Budget & Cost Reports > Division Mgr JIP Reports This new log will allow you to track a couple of things in one log. 1. Subcontract Commitments (SC) & Subcontract Change Orders that are being billed or have been paid but are not executed Filter the "Department Code" to your group of Department codes or group you want to review Filter the "Executed date" column to Null Billed Flag "Y" means that it is unsigned and currently up to be paid / Billing Amount shows how much of the issued amount is being billed for Paid Flag "Y" means that it is unsigned and has already been paid out / Paid Amount show how much of the issued amount has been paid Remove the Billed Flag to see all commitments/SCO's that are not executed for your departments. Created by column at the end is the person that initially submitted the commitment. NOTE: if you click on the Subcontract code, it will take you to that commitment directly. If you go to the Review/approve tab it will give you who submitted it initially and everyone that might have approved it along the way. 2. After the updated SCO WorkFlow Exception Request change that went live on 5/6/2024, there was concern that Project Teams would take advantage and keep all their SCO's under 74,999.00 because then none of them would go through the exception request process. This log will allow you to review all SCO's that are by Less than or equal to: 74999.00 (no comma) (You can also see what rows have not been executed) NOTE: if you click on the Subcontract code, it will take you to that commitment directly. If you go to the Review/approve tab it will give you who submitted it initially and everyone that might have approved it along the way.