Job Project Setup - (Bid/"P" Jobs) Manual Adjustments until fixed
Job Start Project - Items needing manual changed until fixed
All BidJobs (P Jobs)
Job > Enter Job >Job Detail Tab (P Jobs Only)
STEP 1: Expand Job (ADF)
STEP 2: Click enter Job
STEP 3: Search for the P job you need
STEP 4: Change Billing Method to Manual A/R Invoice
STEP 5: Copy Default Dept. #
STEP 6: Click on Accounts Tab

STEP 7: Paste the Dept # into WIP revenue Adjustment Department field
STEP 8: Click on WIP Tab

STEP 9: Double check the Exclude from WIP box is checked
STEP 10: Paste the Dept # into WIP Unposted Costs Department
STEP 11: Paste the Dept # into WIP Unposted Revenue Department
STEP 12: Click Save
STEP 13: Click Exit
Note: You can also Click Table Mode if you need to search for another project #

CMiC Field > Project Maint. > Security Tab (Support Desk)
Note: To find the information to add to the JSP Security tab you have to start in Enterprise
STEP 1: Expand Job Costing (ADF)
STEP 2: Expand Job (ADF)
STEP 3: Click on Enter Job
STEP 4: Search for your P job #
STEP 5: Click the Action button

STEP 6: Click the Security Tab
STEP 7: Make note of the other region that is checked (Other than Master)
STEP 8: Exit

STEP 9: Search for your P job
STEP 10: Click View Current Project
STEP 11: Click Security Tab
STEP 12: Click Edit

STEP 13: Add in the region you noted from Enterprise
STEP 14: Click Save