BIM 360 Glue: File Transmission Legal Requirements
BIM 360 Glue: File Transmission Legal Requirements
Champion
and Pursuit Team
Steps
Involved:
STEP 1: Collect all designer file transmission
/ BIM disclaimer forms
STEP 2: Modify
the Swinerton disclaimer form specific for each subcontractor and consultant
who will be utilizing the 360 Glue site
STEP 3: Send all disclaimer forms to each
subcontractor for signature and return
Why
this step is important:
1. This will protect
Swinerton and our Clients from unnescessary risk from subcontractors utilizing
the files to estimate, fabricate and install from
Do's:
1. Collect the required
sign offs as early as possible so that file transmissions can take place as
needed
Don’ts:
1. Send or give access
to electronic CAD or BIM information for any subcontractor prior to receiving
their returned, executed disclaimer forms.