Is My Project Ready to Close Checklist
Modified on: Thu, Aug 13 2015 4:28 PMEmail the following items to Financial Manager to Close Project
- Checklist below completed
- Final Project Status Report
- Commitment Summary Report
- Commitment CO Report
Prior to requesting your project to be closed by the Financial Manager, verify the following:
1. Project Status Report:
☐a. CONTRACT: Current Contract Value = Revenue Forecast = Gross Billing
☐b. COSTS: Spent to Date = Spent/Committed Total = Cost Forecast
☐c. No Amounts in Anticipated Change Orders/ No open PCIs (All PCIs in approved or cancelled status)
☐d. No Allowance or Contingency in Cost Forecast
☐e. No unbilled Retention
☐f. No open RFIs, all Submittals closed and no open Daily Journals
2. Commitment Summary Report:
☐a. No retained amounts for any Subcontractor
☐b. No balance to complete for any Subcontractor
3. Commitment CO Status Report:
☐a. No Pending/Unposted Subcontract Change Orders for any Subcontractor
4. Textura:
☐a. Subcontract Listing: No retained amounts and no balance due for any Subcontractor
5. Billing and Payment Status Report:
☐a. Billing and Payment Status Report matches Gross Billings on Project Status Report
6. Verify final costs have been applied to your job:
☐a. Verify final Insurance cost posted to job
☐b. Verify final PLP/PSI credits posted to job
☐c. Verify final Builders Risk insurance cost posted to job (if applicable)
☐d. Verify final Subguard & Bond charges posted to job (if applicable)
☐e. Verify final Textura Costs posted to job
☐f. Verify other misc. final charges (warranty, final photography, final payroll charges, taxes, etc.)
CMiC/Project Maintenance/General Tab (Click the current project and click View Current Project)
- Actual Substantial Completion Date Input.
- Actual Final Completion Date Input (Construction Completion)
- Method Used to Determine Final Completion
- Project Status Report
(Front page)
1. |
CONTRACT: Current Contract Value = Revenue Forecast = Gross Billing |
2. |
COSTS: Spent to Date = Spent/Committed Total = Cost Forecast |
3. |
No Amounts in Anticipated Change Orders/ No open PCIs (All PCIs in approved or cancelled status) |
4. |
No Allowance or Contingency in Cost Forecast |
5. |
No unbilled Retention |
(Back page)
1. |
No open RFIs, all Submittals closed and no open Daily Journals |
- Commitment Summary Report
1. |
No Retained Amounts for any Subcontrator |
2. |
COSTS: Spent to Date = Spent/Committed Total = Cost Forecast |
- Commitment CO Status Report
1. |
No Pending/Unposted Subcontract Change Orders for any Subcontractor |
- Textura
1. |
Subcontract Listing: No retained amounts and no balance due for any Subcontractor |
- Billing and Payment Status Report
1. |
Billing and Payment Status Report matches Gross Billings on Project Status Report |